The Project

The project involved the demolition of existing buildings and maintenance of a retained façade fronting onto Knightsbridge. A new structure inserted behind the façade and refurbishment of two buildings in William Street, will provide high quality residential, office and retail space. 

Blue Sky Building’s role was to oversee the piling and associated works. These works included adjustment of the existing retained façade system to enable the piling to be completed. Full logistics, monitoring of noise, dust, vibration and movement of existing buildings and erection of a new façade access scaffold. This enabled the client to procure a new main contractor, whilst maintaining progress of the project.

The Stats

Value

Value

£2.6m

£2.6m

Commencement

Commencement

September 2017

September 2017

Client

Client

Cheval Property Management Ltd

Cheval Property Management Ltd

Completion Date

Completion Date

April 2018

April 2018

Project Team

Architect

Architect

Dixon Jones

Dixon Jones

Quantity Surveyor

Quantity Surveyor

Boyden Group

Boyden Group

Structural/Civil Engineer

Structural/Civil Engineer

WSP

WSP

Mechanical/Electrical Engineer

Mechanical/Electrical Engineer

Long & Partners

Long & Partners

Project Leadership Team

Benn Chandler